| |

6-year statute bars contractor indemnity
By Steven
G. Wraith
Washington’s six-year statute of repose for
construction claims applies to claims of both written and equitable
indemnity, the Washington Court of Appeals has held in Ledcor v.
Nidash, 48337-4-I (Oct. 2002). The case could have far-reaching
implications for the defense of construction-defect claims.
The Ledcor court held that the six-year contractor’s
statute of repose, RCW 4.16.300 - .320, bars such indemnity claims
if the underlying settlement or judgment on which indemnity is based
occurs six years after substantial completion of the project. That
statute bars all claims "arising from" constructing improvements
to real estate that do not "accrue" within six years after
substantial completion. The court also reaffirmed that the "discovery
rule" applies to breach-of-contract claims in such cases.
In Ledcor, apartment owner Parkridge Associates sued
Ledcor, a contractor, for workmanship failures and construction
defects. Ledcor, in turn, sued subcontractor Freeman Roofing for
breach of contract and contractual and equitable indemnity. The
date of substantial completion on the project was December 30, 1993,
but Freeman continued to work on the project until December 5, 1994.
Parkridge sued Ledcor on November 29, 1999. On May
19, 2000, Ledcor tendered defense of the suit to Freeman, which
provided roofing, waterproofing, and other work on the project.
Freeman did not accept that tender, so Ledcor commenced a third-party
action against Freeman on August 19, 2000. On December 22, 2000,
Parkridge and Ledcor reached a mediated settlement. Freeman did
not participate in the settlement. Ledcor then pursued its third-party
claim against Freeman, alleging that Freeman’s defective work
accounted for a significant portion of the settlement payment to
Parkridge.
|
|
|
|
|
|
|